• Non ci sono risultati.

Analisi LCA e LCC per la programmazione di interventi sostenibili per il patrimonio architettonico

N/A
N/A
Protected

Academic year: 2021

Condividi "Analisi LCA e LCC per la programmazione di interventi sostenibili per il patrimonio architettonico"

Copied!
10
0
0

Testo completo

(1)

BY NC

in_bo New Frontiers of Construction Management Workshop 2018, vol. 09 n° 13

LCA and LCC Analysis for the

Programming of Sustainable

Interventions on Building Heritage

and moisture spots caused by condensation

(2)

95

a society that sees a continuous and uncontrollable growth in consumption sustainable consumption, in which environmental and social needs. This is

sector, that is responsible at European

to the comparison residential (which

maintenance strategies and constructive environmental resources.

The present study is aimed at reiterating methodologies as decision support tools

the economic and environmental impact

building component. The objective is to

without a thermal insulation system, was

To solve the problem described

hypothesised, thus returning, according

Figure 1: Old demaged sheath Figure 3: Original section

parameters relating to the materials

insulating layer to be inserted in the two

placing on the cementitious support,

(3)

Alternative A Ecoinvent system process Kg Bituminouswaterproo-Acrylic varnish Alternative B membrane Ecoinvent system process Kg

in_bo New Frontiers of Construction Management Workshop 2018, vol. 09 n° 13

time, reducing in this way the possibility layer, retains its characteristics and

insulating capacity and because it is able resistance to compression and humidity.

bituminous membrane. The decision not to use a single panel is dictated by maintenance and economic issues that will be dealt with later. Moreover, given

middle and the others in the corners, at a

This stratigraphy allows to protect changes, keeping it at temperatures

the sealing layer. To protect the insulating then a heavy protection in washed round gravel, which also allows access to the The thermophysical parameters relating

limit

necessary step to be able to construct

Maintenance, which includes the

Decommissioning, which includes

analysis and consists in the quantitative entering and leaving the two systems. For this reason it was necessary to associate the materials and processes, to the data present in the databases

material the correspondence with the source and the quantity required.

The thermophysical parameters relating We obtain Unit thermal transmittance U

limit

Figure 4: Alternative A Figure 5: Alternative B

(4)

97

Alternative A RES U 76,6 Km Bituminous membrane

Acrylic varnish Malvin

Alternative B

Bituminous

membrane RES U 76,6 Km

Transport, lorry 3,5- 15,5 Km Semac Roccarainola

RES U

To reduce the environmental impacts due to transport, the materials used

recovered, as well as processed, within put in place.

Furthermore, the energy consumption

demolition equipment and the

The investigations carried out to date,

to the stratigraphy in which it is inserted

durability, the best results were obtained with the systems where the mantle

with traditional stratigraphy and without protection, where the mantle is made

1995 include the results published by

cases, according to the report, there are no protection systems.

protected bituminous membranes, ie

radiations and to the consequent high must be protected with acrylic paints.

(5)

Bituminous

membrane Trasport, lorry

3,5-B.Recycling

bituminous membrane Eurometal

RES U

Trasport, lorry 3,5- strutture

B.Recycling

in_bo New Frontiers of Construction Management Workshop 2018, vol. 09 n° 13

environmental savings obtained with the

were planned during the maintenance

maintenance work were considered sent

For the decommissioning phase a manual and mechanical demolition was considered, with the consequent on the trucks.

The materials were sent to recycling

real environmental balance with the help

environmental impacts caused by the two intervention alternatives studied was assessed. This evaluation starts the inventory phase and allows, through

danger.

With the Eco-indicator 99 evaluation it was possible to quantitatively associate

environmental releases to certain impact

impact associated with the systems studied.

belongs to the materials used. Alternative A

the insulating panel determined the highest impact values, in particular with During the maintenance phase, the greatest damage was generated by the with the protective acrylic paint.

recyclable materials. Alternative B

was determined by the insulating

carcinogenic damage to humans and maintenance phase the greatest

(6)

99

19,9 Ecosystem quality Resources TOTAL 123,45 105,04 Ecosystem quality 7,67 6,61 Resources TOTAL 136,37 118,31 73,373 Ecosystem quality 35,751 Resources 139,57 TOTAL 318,05 222,123

the impact categories have been membrane, since it is the only

non-Subsequently, the environmental

impacts that compete with the two design alternatives have been traced

Ecosystem Quality, measured in

Resources, measured in MJsurplus.

The results are shown as a single

Alternative A

the vapor barrier.

maintenance interventions responsible and the greater damage to human health to replace the pre-bitumed insulating acrylic paint.

During the decommissioning phase, the

Alternative B

particular, Resources was the most

the maintenance intervention with the

greatest environmental impact.

membrane has determined damage to the remaining materials were negligible.

a comparative assessment was made between the two design alternatives according to the environmental impacts

the production phase, the alternative A presented the largest environmental load in

design solutions and at the same time

minerals.

alternative A was the design solution

phase, where the gap between the two alternatives was more pronounced not

to resources but also in that relating to human health.

(7)

11,1 Ecosystem quality Resources TOTAL 24,04 17,91 Alternative A acrylic paint remake plaster Alternative B remake plaster

in_bo New Frontiers of Construction Management Workshop 2018, vol. 09 n° 13

Table 8: Phases costs

because alternative A needs more

two restoring works on the bituminous painting operations must be added with acrylic protective paint. two years. Even in the decommissioning phase the alternative B was the most sustainable solution, with a total environmental

that they presented the main problems were those related to human health and to recycle the bitumen-based material,

the two alternatives have been divided

Maintenance, which includes the

costs triggered by maintenance

Decommissioning, which includes

phases.

each intervention, thus obtaining the

costs related to energy consumption

the cost related to the consumption

the cost related to the consumption

-•

-sary to proceed with the discounting

-rent maturities over time.

(8)

€ 5.636,75 Maintenance

Decommissioning

Ecosystem quality 56,53

Resources

Table 9: Phases costs

the alternative A, in blue the alternative Taking also into consideration the

maintenance phase and the discounted obtained the global costs.

interventions.

RESULTS

methodologies to the present study has made it possible to evaluate and compare the environmental and

analysis showed that alternative B represents the least impacting choice environmental damage related to the

The greater environmental criticality

intensive maintenance activity and by materials.

solution to the European purposes

this alternative constitutes the most economically advantageous solution

maintenance costs, between the two

(9)

in_bo New Frontiers of Construction Management Workshop 2018, vol. 09 n° 13

Figure 9: Global costs

higher weight.

economically advantageous solution approach that allows you to have an

allows to limit the maintenance costs in the construction phase.

Added to this is the need to make the she is aware that a certain design choice impact on the environment associated

included in the comparative evaluation conducted, with which it was possible to

Moreover, the decision to intervene on the building envelope with a thermal redevelopment intervention, involves the environment, since decreasing that is emitted into the atmosphere.

(10)

Termotecnica.

Codice dei contratti

. . , dicembre Recycle. Editore. , M. , M. R.

Ed. Franco Angeli.

La Chimica & La , (available (available (available (available

Figura

Figure 4: Alternative A Figure 5: Alternative B
Table 8: Phases costs
Table 9: Phases costs
Figure 9: Global costs

Riferimenti

Documenti correlati

Another notable advantage introduced is the fact that the user would receive digital access copies specifically prepared for this process (for example, compressed and watermarked,

The aim of the research was to investigate the effects of an experimental educational programme of Adapted Physical Activity (APA), integrating the potential of

Thus, the character’s death is once more a symbol for a final access to the inside, just like it was for Edgardo Limentani: for them both suicide is the statement of a failure

Comparison of data with simulation for the distributions of the BDT discriminants in the (upper left) 2-jets 2-tags, (upper right) 2-jets 1-tag, and (bottom) 3-jets 2-tags

Assessment of fetal compromise by Doppler ultrasound investigation of the fetal circulation: arterial, intracardiac and venous blood flow velocity studies.. Doppler studies

Here, to make up for the relative sparseness of weather and hydrological data, or malfunctioning at the highest altitudes, we complemented ground data using series of remote sensing

[r]

The Deputy Prime Minister took the view that the Government had agreed to co-operate with the EU by allowing euro zone countries to use the EU institutions to enforce the