• Non ci sono risultati.

First Column: Intervention Logic

Nel documento 1.1 Purpose of the guidelines (pagine 82-86)

5.3 THE PLANNING STAGE

5.3.2 First Column: Intervention Logic

If-then causality

The first column of the Logframe matrix summarises the ‘means-end’ logic of the proposed project (also known as the ‘intervention logic’).

When the objective hierarchy is read from the bottom up, it can be expressed in terms of:

If reversed, we can say that:

This logic is tested and refined by the analysis of assumptions in the fourth column of the matrix (described below in section 5.3.3).

IF

adequate inputs/resourcesare provided,

THEN

activitiescan be undertaken;

IF

the activitiesare undertaken,

THEN

resultscan be produced;

IF

resultsare produced,

THEN

the purposewill be achieved; and

IF

the purposeis achieved,

THEN

this should contribute towards the overall objective

IF

we wish to contribute to the overall objective,

THEN

we must achieve the purpose

IF

we wish to achieve the purpose,

THEN

we must deliver the specified results

IF

we wish to deliver theresults,

THEN

the specified activitiesmust be implemented; and

IF

we wish to implement the specified activities,

THEN

we must apply identified inputs/resources.

Management influence

The Logframe helps to indicate the degree of control managers have over the different levels of the project’s objectives. Managers should have significant direct control over inputs, activities and the delivery of results, and should be held appropriately accountable for effectively managing theses elements of the project.

However managers can only exert influence over the achievement of the project purpose through the way in which the delivery of results is managed. Project managers generally have no direct influence over the contribution the project makes to the overall objective, and can only be expected to monitor the broader policy and programme environment to help ensure the project continues to be contextually relevant.

The necessary and sufficient conditions within the vertical logic are another way of viewing this issue.

These indicate that:

• Achieving the purpose is necessary but not sufficient to attain the overall objective;

• Producing the project results is necessary but may not be sufficient to achieve the purpose;

• Carrying out project activities should be necessary and sufficient to deliver the results;

and

• Inputs should be necessary and sufficient to implement the planned activities.

However, in applying this general logic it is important to recognize that management responsibilities in the context of many development projects are often shared between stakeholders. While this is in some ways the essence of a ‘partnership’ approach, it is important that actual management responsibilities are made as clear as possible, and that such responsibilities should generally rest with local implementing agencies.

Project results and ‘contracted’ outputs

In the context of management influence, it can be useful to make a distinction between project results and contracted outputs. A project result (as shown in the Logframe matrix) is generally a product of the actions/activities of a number of different stakehold-ers (i.e the partner government’s ministry of health, local health management boards and the services of Technical Advisory staff funded by a donor).

In such circumstances it is usually inappropriate for the EC to hold any contracted TA/project managers wholly responsible for the project result, but rather for

‘contracted’ output(s). Contracted outputs should specifically define what the contractor must deliver (within their control) in order to contribute to the achievement of project results.

This concept is further illustrated in Figure 26 below:

Project purpose

Project result

Project activities

Contracted output

Logframe objectives Contract/Terms of Reference for

EC supplied services

Contracted activities

Specifies what stakeholders jointly commit to

implementing

Specifies what the EC commits to delivering through TA/a contractor

Figure 26 – Relationship between project results and contracted outputs

Project components

It can be useful to group sets of closely related project results, activities and inputs into project

‘components’, particularly for larger/more complex projects. These ‘components’ can also be thought of as project ‘strategies’.

Components can be identified on the basis of a number of possible criteria, including:

• Technical focus (i.e. a research component, a training component and an engineering component within a watershed management project).

• Management responsibilities/organisational structures (i.e extension, research and credit components of an agricultural project to reflect the structure of a Department of Agriculture).

• Geographic location (i.e a component for each of 4 countries involved in a regional people

trafficking project).

• Phasing of key project activities (i.e. a

component for each of the main stages in a rural electrification project which requires a feasibility study, pilot testing, implementation and

maintenance stages.

Identifying and agreeing on what might be useful/appropriate components to include in the project should be based on the objectives and strategy analysis, consultation with key stakeholders and consideration of

‘what makes sense’ from a management perspective.

For larger projects which do have more than one component, consideration can be given to having more than one project purpose (one per component).

This can be a practical way of disaggregating and allocating a significant number of different project results.

Objective trees and reference numbers

When thinking about (or helping to explain to others) the logical structure of the first column of the matrix, it is often easiest to present it in the form of an objective tree. This much more clearly demonstrates the ‘means-ends’ hierarchy.

The use of reference numbers in the Logframe (and associated activity, resource and budget schedules), to clearly link inputs, activities and results, is also an extremely useful convention. An example of reference numbering is shown in Figure 27:

Figure 27 – Objective tree with reference numbering

Overall Objective

In this example of a Logframe objective tree, it would also be possible to restructure the objective hierarchy to either: (i) have 3 separate purposes (one for each component) rather than one unifying purpose; or (ii) to include another level in the objective hierarchy, such as a ‘component objective’. The key issue here is to allow those responsible for using tools such as LFA to have some flexibility to adapt the formats to their practical needs. If the ideas are good and the logic is sound, the number of levels in the objective hierarchy or the exact formats used should not be of any great concern.

Writing clear statements and avoiding a common problem of logic

Objective statements in the Logframe matrix should be kept as clear and concise as possible.

It is also useful to standardize the way in which the hierarchy of project objectives is described.

A useful convention to follow in this regard is:

(i) for the Overall Ojective to be expressed as

‘To contribute to…..`; (ii) the Purpose to be expressed in terms of benefits to the target group being

‘Increased/improved/ etc……….’, (iii) Results to be expressed in terms of a tangible result

‘delivered/produced/conducted etc’, and (iv) Activities to be expressed in the present tense starting with an active verb, such as ‘Prepare, design, construct, research …..’. An example is shown in Figure 28.

Objective hierarchy Example of how to write statements

Overall objective To contribute to improved family health, particularly of under 5s, and the general health of the riverine eco-system

Purpose 1. Improved river water quality

Results 1.1 Reduced volume of waste-water directly discharged into the river system by households and factories

1.2 Waste-water treatment standards established and effectively enforced Activities 1.1.1 Conduct baseline survey of households and businesses

(may not be included 1.1.2 Complete engineering specifications for expanded sewerage network in the matrix itself,

but rather presented 1.1.3 Prepare tender documents, tender and select contractor in an activity

schedule format) 1.1.4 Identify appropriate incentives for factories to use clean technologies

1.1.5 Prepare and deliver public information and awareness program

1.1.6 etc

Figure 28 – Writing objective statements

A common problem in formulating objective statements is that the purpose statement is formulated as a re-statement of the sum of the results, rather than as a higher-level achievement.

For example:

BAD PRACTICE GOOD PRACTICE

Purpose is sum of results: Purpose is consequence of results:

“Water treatment is improved and levels of “Improved quality of river water”

direct discharge into the river reduced”

Results:

1.1 Direct discharge of waste-water into the river reduced 1.2 Waste water treatment standards improved and enforced

1.3 Public awareness of environmental management responsibilities improved

Figure 29 – Relationship between assumptions and objective hierarchy

Overall Objective

Purpose

Results

Activities Assumptions

Assumptions Assumptions

Pre-conditions – need to be met before resources are committed and activities initiated

e.g if activities are undertaken AND assumptions hold true, then results can be achieved, etc

Inputs

Nel documento 1.1 Purpose of the guidelines (pagine 82-86)