• Non ci sono risultati.

The closed loop system at ISR

N/A
N/A
Protected

Academic year: 2021

Condividi "The closed loop system at ISR"

Copied!
9
0
0

Testo completo

(1)

The closed loop system at ISR

We moved the system at ISR in January.

Preliminary tests has been done in order to verify the possible use in the “ISR conditions”:

1. Total flow of 150-200 l/h

2. Connect and disconect frequently the RPC from the gas system

The closed loop worked at the GIF for many months with a total flow of 40 l/h and a fresh mixture input of 2 l/h (5% of the total flow)

CMS week 14 March 2005 Roberto Guida

(2)

Total flow of 150-200 l/h

• The system was tested succesfully with an argon bootle (short test: only few hours)

• During this test 4 RPC were connected

• A total flow of 200 l/h was reaced with an

input flow of 10 l/h (5% of the total flow)

(3)

Connect and disconect frequently the RPC from the gas system

• The RPCs under test change every 2-3 weeks

• It must be avoided the connection of an RPC full of air to the closed loop system (contamination of all the circuit)

• It is impossible to stop the gas flow (the

system is sensible to pressure variation)

(4)

Project

• We have forseen an open loop line for the first connection of an RPC and two three ways valves (for each gas line) for the

commutation between the open loop to the closed loop

• We have already tested this solution with two channel connected to the closed loop and two valves per channel for the

commutation

(5)

Input Open Loop

Output Open Loop

Closed Loop Rack Output

Closed Loop

Input Closed

Loop

Distrib. Rack Input Part Distrib. Rack

Output Part

(6)

RPC

bubblers

Three ways valve Rotameters

Ch 1 Ch 2

Cl,

Op, Cl, Op, Op, Cl, Op, Cl,

Flux contr. Flux contr.

Legend

(7)

Status of the system

• Test of the three ways valve  OK

• Test of the connection to the general input and output lines  OK

• 3 new lines for the closed loop (input and output)  OK 1 new line for the open loop (input and output)  OK Each line is about 100 mt long

• Construction of the commutation pannels (between closed and open loop)  OK

(8)

• Construction of the commutation pannels (between closed and open loop)  OK

Input valves

output valves Bubblers for the open line

10 channels

(9)

• Integration between the present system and the commutation pannels  Wednesday 16

th

March

• Development of a system for switch off the HV in case of a stop of the closed loop

• Test of the final system

Riferimenti

Documenti correlati

Response to “ Can be Silent Brain Lesions a Target to Guide Anticoagulation Treatment in Patients with Low-Risk Atrial Fibrillation to Reduce Cognitive Impairment?” by Ammirati et

The paper is organized as follows: in Section 2 we summarize the main definitions and properties related to the G-expectation framework, as well as the Itˆ o stochastic calculus

First, the spikes activity was recorded from the labellar l-type sensilla following stimulation with metabolizable mono- and disaccharides (maltose, sucrose, trehalose,

filing date "X" document of particular relevance; the claimed invention cannot be considered novel or cannot be considered to involve an inventive. "L" document

Starting from a three-dimensional reconstruction of the actor in the scene, acquired with an innovative conguration composed of Microsoft Xbox 360 Kinect devices and obtained

Per analizzare la possibile interazione tra il C-terminale e la prima ansa intracellulare di TMEM16A, sono state effettuate delle simulazioni di dinamica

Also, native-NPFS ACO performs better in 75% of Taillard benchmark problems than the current best non-native approach, the ACO with pheromone trails initialized

In particular, the contribution of different features of the recorded signals (i.e. spikes vs bursts) has been thoroughly investigated in the course of this