RE1/2 and RE1/3

Gap Status & QC - 2005 CMS week March 2005

Piritta Kaarlola

(2)

Gap QC

Gap QC consists of HV, Spacer and Gas Leakage test

HV test

Applied HV values: 2000, 4000, 6000, 8000, 8500, 9000 & 9100

Resulted currents must stay within the range from 0.50 µA to 3.00 µA

Spacer test

Gas input and output are connected with 20 mbar overpressure

Allowed change: ± 0.5 mbar

Gas Leakage test

Gas input and output are connected with 20 mbar overpressure

Allowed gas leakage: max. -0.5 mbar

 Another QC issue: bent gaps

Allowed bending <10mm For the moment used for spares

(3)

RE1/2 Gap status

 Chambers

 None ready – Production not yet started

 60 needed (180 gaps)

 Gaps

 Current holdings

Small: 18

Medium: 13

Big: -

 Still needed

Small: 42

Medium: 47

Big: 60

(4)

RE1/3 Gap status

 Chambers

 13 ready chambers (39 gaps)

 47 needed chambers (141 gaps)

 Gaps

 Current holdings

Small: 9

Medium: 7

Big: 2

 Still needed

Small: 38

Medium: 40

Big: 45

(5)

RE1/3 QC – HV Test

Average currents of HV tested gaps

(6)

RE1/3 QC - Spacer and Gas Leak Test

 Spacer Test:

 1 small gap rejected

 Gas Leak Test

 Very little or no leak – no rejected gaps

 Bent gaps

 5 big gaps

Riferimenti

Documenti correlati

− Le! società! per! azioni:! gli! enti! locali! sono! affiancati! da! soci! privati! o! enti! pubblici! non! legati! allo! stesso! territorio.! Si! intende! così! permettere!

 Setting up a long scan with high statistics for Cluster Size, Efficiency, Strips Profile and Time Distribution.  Recording all these data and store in

0.2 Initial draft provided by Archana Sharma is edited to add the configuration database requirements jointly for Forward (Endcap) RPC (requirements given by Archana Sharma) and

[r]

The alterna- tive approach is to deliver the planned dose distribution to an anthropomorphic phantom and to compare the phantom measured dose distribution to the dose dis-

IL &#34;SOIL MIXING&#34; PER IL CONSOLIDAMENTO DEI TERRENI Applicazioni, Progettazione e Controlli CORSO DI AGGIORNAMENTO PROFESSIONALE Ordine Geologi del Lazio Roma, 24

[r]

[r]