• Non ci sono risultati.

18 RE1/2 and 18 RE1/3 Installation April end 60 RE1/2 & 60 RE1/3

N/A
N/A
Protected

Academic year: 2021

Condividi "18 RE1/2 and 18 RE1/3 Installation April end 60 RE1/2 & 60 RE1/3"

Copied!
12
0
0

Testo completo

(1)

AS

2005 Milestones

Production

18 RE1/2 and 18 RE1/3 Installation April end 60 RE1/2 & 60 RE1/3

Installation October-November Cosmic Tests / Magnet Test Preparation

April 05 Sep 05

RE- 1048

HALF: RE1/2 + and RE1/3 ready for installation RE-

1049 RE2, 3 installed on YE+

Schedule V34.1

2004 Milestones

3 RE1/2 & 1 RE1/3 pre production chambers tested

Korean gaps deliveries ISR Assembly Lab on

schedule

CSC+RPC+LB Beam Tests Cosmic QC 20 RE1/2 +10

RE1/3

On behalf of On behalf of

Peking University Colleagues Peking University Colleagues

And all at ISR And all at ISR

(2)

RE1/2 Completed chambers RE1/2 Completed chambers

ready for quality control ready for quality control tests in the cosmic stand tests in the cosmic stand

Cosmic stand and DAQ Cosmic stand and DAQ

Dec. 2004

HV connector HV connector

Last step Last step

(3)

AS

Ch am be rs Ch am be rs

36 needed @ X5 36 needed @ X5

April 2005 April 2005

Constructed Constructed Planned

Planned

Production Status:

Production Status: 20 RE1/2 + 30 RE1/3 Assembled

Preparation

gas pipes – 120 chambers Cables – 60 chambers

Mechanics ..

Cover closing Alu plates Chamber production rate Expected 5 per week

March 20 RE1/2

mass production re-launch GOAL: June RE1/2 complete

April end RE1/3 Gaps expected

mass production re-launch GOAL: Sept 30 RE1/2 complete

GOAL: Dec 05 All certified!

(4)

Database developed to store RPC production information Database developed to store RPC production information

http://forwardrpc/cms_forward_rpc/production_db/Main_db.htm

http://forwardrpc/cms_forward_rpc/production_db/Main_db.htm

(5)

AS

Create plots from Create plots from

cosmic test data cosmic test data

Strip Strip response response

profile

profile

(6)

Cosmic QC

See Andrey’s talk

Noise < 10Hz/cm Noise < 10Hz/cm

22

% %

  A A HV 9.2kV

HV 9.2kV

(7)

AS

Cosmic Tests : Andrey 4 Checklists

At different stages of production

Waiting for Final Destination: Point 5

(8)

Version Number

Description Author Date

0.1 First draft about RPC sub-detector description and related database requirements after having discussion with Frank Glege, Anil Kumar, Saima Iqbal and Marcello

Abbrescia

Archana

Sharma 31-JAN-2005

0.2 Initial draft provided by Archana Sharma is edited to add the configuration database requirements jointly for Forward (Endcap) RPC (requirements given by Archana Sharma) and for Barrel (given by Marcello Abbrescia)

and on the basis of discussions with Frank Glege, Andrew Branson and Norbert Zoltan Toth.

Saima Iqbal

14-Feb-2005

0.3 Comments to v0.2 by Archana Saima

+ Archana

15-Feb-2005

0.4 Comments to v0.3 by Marcello Saima +

Marcello

17-Feb-2005

0.5 Ambiguities mentioned in v0.2 resolved. Add Configuration database schema (Initial version is

provided after editing discussion based on requirements among Norbert, Andrew, Saima and

Marcello ) and add condition database schema requirements as provided by Marcello

Saima 06-Mar-2005

0.6 Question mentioned in V0.5 are resolves Saima 13-Mar-2005

Barrel and Forward (Endcap) RPC’s Configuration and Condition database requirements

for CMS Core DB Team

Document history - Following DB Workshop Jan 24-28

(9)

AS

Schema for RPC Barrel and Endcap

See Marcello’s talk – DB meeting

Wednesday 16 at 8.30

(10)

YE+2

YE+2

49m 10m

18m 15m

20m SX5 Cables & Services

horizontal distances inside SX5 Counting

House

(see next page)

YE+2

magnet test position

YE1

HB HB

Magnet Tests

10m

YE+1

6 RE1/2 Chambers (One sector 60o)

6 Link Boards available

(11)

AS

15m

8m SX5 Cable Paths to be defined

horizontal distances Counting House only

runcontrol

detectors magnet

DAQ

Counting House The Green Barrack

(12)

Summary and Conclusions

• Mass production gas gaps Korea full steam

• Assembly RE 1 ramped up @ ISR lab and has reached 5 chambers per week

• The final RE 1/2 RPC has been mated to ME 1/2

• RE1/3 installation exercise performed

• Preparation for magnet tests started

RE 1 production expects to meet the CMS master

schedule for its installation and commissioning

Riferimenti

Documenti correlati

a) Per verificare che i quattro punti sono complanari basta determinare un’equazione del piano π passante per tre di essi, per esempio A, B e C, e verificare che D appartiene a

Tamburrini1, 1Pediatric Neurosurgical Unit, Catholic University Medical School, Rome, Italy, 2Neuroendoscopy Unit, Department of Pediatric Neurosurgery, Santobono-Pausilipon

[r]

Pavia, Pavia University

 Allowed bending &lt;10mm For the moment used for spares.. RE1/3 QC –

Chimney RB2-RB3 ready middle April Chimney RB1-RB4 ready middle

0.2 Initial draft provided by Archana Sharma is edited to add the configuration database requirements jointly for Forward (Endcap) RPC (requirements given by Archana Sharma). and

EU MEPS (European Minimum Energy Performance Standard) sets mandatory minimum efficiency levels for new motors placed on the European market.. The third and final stage of EU MEPS –